Contractors - Sub-contractors working under the direction of Zachau are:
COLEX
Site work
Hadlock
Front Entrance Masonry
AP Masonry
Masonry
Pond Cove Millwork
Millwork
Tri-City Drywall
Drywall
Quality
Insulation
Stanley
Elevator
Dean & Allyn
Sprinkler System
Titan Mechanical
Mechanical
L&B Electrical
Electrical
J & M Flooring
Flooring
Hahnel
Roofing
Tibbetts
Painting
Construction Status
Staging around the 1876 building has been removed
1876 slate roof tiles have been repaired
Foundation for elevator has been poured
Construction of walls for elevator is in progress
Trim repair work and brick/mortar repair work is in progress for 1876 Pennell
Replacement windows for 1876 have been installed
Final trim painting will be done in the spring
Structural steel and roof trusses for the 1954 segment are in place
1954 roof underlayment is progress
Framing for 1954 walls in progress
Rough covering for 1954 walls in progress
Firewall for new stairway has been installed
Front entrances to 1876 Pennell will be completed in the spring
Site work and the finish coat for the parking lot will be completed in the spring
Zachau's on site supervisor is Mike Packard.
The next community tour of the Pennell Construction site is scheduled for April 17 between 9 AM and 11 AM for those interested in viewing the status of the work.
Projected Construction Completion Date – Mid July 2010