The next community tour of the Pennell Construction site is scheduled for April 17 between 9 AM and 11 AM for those interested in viewing the status of the work.
Contractors - Sub-contractors working under the direction of Zachau are:
COLEX
Hadlock
AP Masonry
Pond Cove Millwork
Tri-City Drywall
Quality
Stanley
Dean & Allyn
Titan Mechanical
L&B Electrical
J & M Flooring
Hahnel
Tibbetts
Site work
Front Entrance Masonry
Masonry
Millwork
Drywall
Insulation
Elevator
Sprinkler
System
Mechanical
Electrical
Flooring
Roofing
Painting
Construction Status
Construction of firewalls for elevator is complete
1954 roof underlayment is complete - shingles installation scheduled to begin week of April 5
Framing for 1954 exterior walls in finished
New stairway to second level 1954 has been installed
Work on repairing front entrances to 1876 Pennell in progress
New siding and trim for 1954 exterior to begin week of April 5
Exterior wall facing for 1954 segment is complete
Basement excavation 1876 in progress
Dry wall work to begin week of April 12
Windows for 1954 to be installed week of April 12
Elevator will be ordered on April 5
1876 demolition work is 60% complete
Opening for the new stairway to 1876 basement is complete
Trim repair work and brick/mortar repair work is in progress for 1876 Pennell
Final trim painting will be done in the spring
Site work and the finish coat for the parking lot will be completed in the spring
Zachau's on site supervisor is Mike Packard.
Projected Construction Completion Date – Mid July 2010