Re-dedication Celebration will be held on July 24!
Contractors - Sub-contractors working under the direction of Zachau are:
COLEX
Hadlock
AP Masonry
Pond Cove Millwork
Tri-City Drywall
Quality
Stanley
Dean & Allyn
Titan Mechanical
L&B Electrical
J & M Flooring
Hahnel
Tibbetts
Site work
Front Entrance Masonry
Masonry
Millwork
Drywall
Insulation
Elevator
Sprinkler
System
Mechanical
Electrical
Flooring
Roofing
Painting
Construction Status
Elevator is being installed
Work on repairing front entrances to 1876 Pennell in progress
Siding and trim for 1954 exterior in progress
Basement concrete slab is finished
Dry wall work in progress
Duct work in progress
Electrical work in progress
HVAC work in progress
Plumbing work in progress
1876 demolition work is complete
Trim repair work and brick/mortar repair work is in progress for 1876 Pennell
Final trim painting is in progress
Interior painting is in progress
Floor installation is in progress
Site work and the finish coat for the parking lot are in progress
Issued a Change Order to add basic renovations to the Second level 1876 Pennell. This work is in progress.
Clock Works have been temporarily removed for renovations in preparation for displaying the clock works on the second floor - 1876 Pennell. Anticipate reinstallation in the fall of 2010.
Zachau's on site supervisor is Mike Packard.
Projected Construction Completion Date – July 16, 2010