Pennell Project Status #7
Design Drawings – Design Drawings and specifications are now totally complete.

Planning Board  - Received conditional approval from the Planning Board on October 22

Guaranteed Maximum Price - bids for Phase 1 work (exterior work for 1876 building, site work and windows for 1876 building) and environmental remediation have been received.  Selected bidders are:   

  • Site Work                                       COLEX
  • Phase 1 masonry                                         Hadlock
  • Staging                                         Seacoast
  • Roof repair - 1876                              Hahnel
  • 1876 Windows                                    Hancock Lumber
  • Phase 1 painting                                        Tibbetts
  • Phase 1 electrical  (exterior conduit/ wiring)  LM Electrical
  • Environmental Remediation                       Morrissey Environmental
Construction Manager (Zachau Construction) has submitted a proposed Guaranteed Maximum Price for the Phase 1 work of  $ 513,756.  

Zachau will conduct a site tour for Phase 2 prospective bidders on Nov. 12,
Bids to Zachau for Phase 2 work are due on Nov. 18.

Zachau plans to offer a Guaranteed Maximum Price for the balance or the work by November 23.  

Construction Status – Staging is in place.  Work is in progress to replace the front entrances to 1876 Pennell, complete exterior brick and trim renovation, implement roof repairs, complete environmental remediation, build additional parking areas and to make selected site revisions.  Parking lot paving is scheduled for November 17.  

While the staging is in place around the tower, clock tower maintenance specialists are inspecting the clock works, performing routine repairs to the clock works and the clock faces and installing additional access ports to the clock faces.

Phase 2 work is expected to begin in late November.  Zachau's on site supervisor is Mike Packard.  

Site Tour - Zachau is planning to schedule a tour of the construction site for interested citizens on a Saturday in December.  

Projected Construction Completion Date – June 2010