Skip Navigation
This table is used for column layout.
Welcome to Gray, Maine
Town Information

Additional Links

Town Hall Hours
Monday - Wednesday
8:30 am - 4:00 pm
Thursday
8:30 am - 6:30 pm
Friday
8:30 am - 12:00

24 Main Street
Gray, ME 04039
Tel (207) 657-3339
Fax (207) 657-2852
Gray Town Seal
 
Photo of Gray Photo of Gray Photo of Gray
Pennel Project Status #9
Guaranteed Maximum Price - The Guaranteed Maximum Price has been signed.  The combined GMP for construction and construction management = $ 2,060,318.  Non Construction costs are projected to be approximately $ 314,000.  Total cost = $2,375,000.   

Contractors - Sub-contractors working under the direction of Zachau are:

                COLEX                           Site work                                               
                 AP Masonry                      Masonry
                Pond Cove Millwork              Millwork                          
                Tri-City Drywall                        Drywall
                Quality                         Insulation
                Stanley                         Elevator
                Dean & Allyn                    Sprinkler System
                Titan Mechanical                        Mechanical
                L&B Electrical                  Electrical
                J & M Flooring                  Flooring
                Seacoast                                Staging
                Hahnel                          Roofing
                Morrissey Environmental         Environmental Remediation
                Tibbetts                                Painting


Construction Status – The clock gear works and hands were reinstalled to return the clock to running order on December 24th.   Staging around the clock tower is being repositioned.  Restoration of the slate roof tiles, trim work and the brick/mortar of 1876 Pennell are in progress.  Final trim painting will be done in the spring.  Replacement of the front entrances to 1876 Pennell will be completed in the spring after the staging is removed.   Site work and the finish coat for the parking lot will be completed in the spring.    

Replacement windows for 1876 segment have been delivered to the site.  Installation to begin on January 11.  

Roof trusses for the 1954 section, structural steel and windows for the 1954 segment have been ordered.  Shop fabrication of the roof trusses will start in mid January.    

Zachau's on site supervisor is Mike Packard.  

The next community tour of the Pennell Construction site is scheduled for February 20 between 9 AM and 11 AM for those interested in viewing the status of the work.

Projected Construction Completion Date – Mid July 2010